Using the accompanying diagram, do the following: Prepare an MRP plan for scissors. Lead times are one day for each component and final scissors assembly,
Using the accompanying diagram, do the following:
Prepare an MRP plan for scissors. Lead times are one day for each component and final scissors assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day Note: There are straight blades and bent blades on hand, and top blade assemblies on hand. Leave no cells blank be certain to enter wherever required.
Use lotforlot ordering for all items.
tabletableScissors LT weekLot size: LotforLotBeg. Inv.,tableGross requirements,,,,,,,,,Scheduled receipts,,,,,,,,,On hand,,,,,,,,,Net requirements,,,,,,,,,Planned order receipts,,,,,,,,,Planned order releases,,
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started