Question
Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram. You may
Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram. You may use a drawing application to produce your network diagram, draw it on paper and paste a photo of your drawing here, or use PowerPoint or Visio.
Ensure that you explicitly state the critical path of your project and show your work. (4 points)
Task ID | Task | Duration | Predecessor |
1 | Plan Expedition Everest project | 10 months | |
2 | Research Nepal Environment and Artifacts | 8 months | 1 |
3 | Design Mountain | 6 months | 1 |
4 | Design Roller Coaster | 10 months | 3 |
5 | Design Yeti | 8 months | 4 |
6 | Design Village | 4 months | 2 |
7 | Approve Design | 1 month | 3, 4, 5, 6 |
8 | Construct Mountain | 14 months | 7 |
9 | Construct Roller Coaster | 12 months | 8 |
10 | Construct Yeti | 12 months | 9 |
Task ID | Task | Duration | Predecessor |
11 | Construct Village | 6 months | 8 |
12 | Inspect Ride | 1 month | 8, 9, 10, 11 |
13 | Test Ride | 3 months | 12 |
14 | Advertise Opening of Expedition Everest | 6 months | 7 |
15 | Open Ride | 0 months | 13, 14 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started