Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram. You may

Using the following task list, calculate the critical path of the Disney Expedition Everest project. Show your work by providing your network diagram. You may use a drawing application to produce your network diagram, draw it on paper and paste a photo of your drawing here, or use PowerPoint or Visio.

Ensure that you explicitly state the critical path of your project and show your work. (4 points)

Task ID

Task

Duration

Predecessor

1

Plan Expedition Everest project

10 months

2

Research Nepal Environment and Artifacts

8 months

1

3

Design Mountain

6 months

1

4

Design Roller Coaster

10 months

3

5

Design Yeti

8 months

4

6

Design Village

4 months

2

7

Approve Design

1 month

3, 4, 5, 6

8

Construct Mountain

14 months

7

9

Construct Roller Coaster

12 months

8

10

Construct Yeti

12 months

9

Task ID

Task

Duration

Predecessor

11

Construct Village

6 months

8

12

Inspect Ride

1 month

8, 9, 10, 11

13

Test Ride

3 months

12

14

Advertise Opening of Expedition Everest

6 months

7

15

Open Ride

0 months

13, 14

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions