Using the Network Diagram and the Time and Cost table below, if you were required to shorten your project, which activity would you crash first?
Using the Network Diagram and the Time and Cost table below, if you were required to shorten your project, which activity would you crash first?
ACTIVITY | NORMAL TIME | CRASH TIME | NORMAL COST ($000s) | CRASH COST ($000s) | CRASHING COST / WEEK DC/DT |
A | 4 | 2 | 8 | 14 | 3 |
B | 3 | 2 | 9 | 11 | 2 |
C | 4 | 4 | 10 | 10 | 0 |
D | 5 | 3 | 10 | 15 | 2.5 |
E | 4 | 1 | 11 | 14 | 1 |
F | 1 | 1 | 6 | 6 | 0 |