Using the PERT formula, calculate the time (t) for each activity Activity Predecessor Most Optimistic Most likely Most Pessimistic Time in days A _ 4

Using the PERT formula, calculate the time (t) for each activity

Activity Predecessor Most Optimistic Most likely Most Pessimistic
Time in days
A _ 4 8 24
B _ 3 10 11
C _ 6 12 24
D A;b 9 14 25
E B;C 11 16 27
F D;E 13 15 35
G F 5 9 19
H G 7 15 23

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions

Question

How does quality of design differ from quality of conformance?

Answered: 1 week ago

Question

How can NAFTA be beneficial to suppliers of Walmart?

Answered: 1 week ago