Question
Using the PERT formula, calculate the time (t) for each activity Activity Predecessor Most Optimistic Most likely Most Pessimistic Time in days A _ 4
Using the PERT formula, calculate the time (t) for each activity
Activity | Predecessor | Most Optimistic | Most likely | Most Pessimistic |
Time in days | ||||
A | _ | 4 | 8 | 24 |
B | _ | 3 | 10 | 11 |
C | _ | 6 | 12 | 24 |
D | A;b | 9 | 14 | 25 |
E | B;C | 11 | 16 | 27 |
F | D;E | 13 | 15 | 35 |
G | F | 5 | 9 | 19 |
H | G | 7 | 15 | 23 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Operations Management Processes and Supply Chains
Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra
10th edition
978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App