Activity | Preceding Activity | Time (weeks) |
A | - | 4 |
B | - | 6 |
C | A,B | 7 |
D | B | 8 |
E | B | 5 |
F | C | 5 |
G | D | 7 |
H | D,E | 8 |
I | F,G,H | 4 |