Question
Using the task duration probability data (in weeks), and precedence data shown below, answer the questions: a. Draw the network and identify the critical path
Using the task duration probability data (in weeks), and precedence data shown below, answer the questions:
a. Draw the network and identify the critical path for the project?
b.What are the expected duration and standard deviation of the project of the critical path?
Activity Low 10 5 4 15 ABCDEFGHIIKIN L M DOGT 17 10 12 5 7 16 5 10 1919 11 10 Most High Likely 22 2792N 25 30 22112112 21 20 10 087166 18 27 11 16 26 268 42 16 18 41 45 38 31 18 1886200 31 38 16 32 38 Preceded. by None ABCCDELUHELH .F I.K. G 1. J Mean S l'is $ CP
Step by Step Solution
3.39 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
Answer To answer the questions we need to first calculate the expected duration and va...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project management the managerial process
Authors: Eric W Larson, Clifford F. Gray
5th edition
73403342, 978-0073403342
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App