Question
Value added activities problem Minutes Move raw materials from RM inventory to Machine A 6 Raw materials wait to be put on machine A 45
Value added activities problem | Minutes |
Move raw materials from RM inventory to Machine A | 6 |
Raw materials wait to be put on machine A | 45 |
Time spent manufacturing product on Machine A | 180 |
Move from Machine A to Machine B | 5 |
Wait time before putting product on Machine B | 480 |
Time spent manufacturing product on Machine B | 120 |
Move from Machine B to Quality control department | 10 |
Time spent inspecting product | 240 |
Move product from QC to finished goods warehouse | 14 |
Total time in minutes | 1,100 |
Calculate the VA time as a % of total time.
Show solutions and calculations.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the valueadded VA time as a percentage of the total time we first nee...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Entrepreneurship
Authors: Andrew Zacharakis, William D Bygrave
5th Edition
1119563097, 9781119563099
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App