ve False QUESTION 12 JRE2 Inc, entered into a contract to install a pipeline for a fixed price of $2,395,000,JRE2 recognizes revenue upon contract completion.
ve False QUESTION 12 JRE2 Inc, entered into a contract to install a pipeline for a fixed price of $2,395,000,JRE2 recognizes revenue upon contract completion. Cost incurred Estimated Cost to Complete 2020 $ 276,000 2021 1.680,000 1,730.000 2022 630,000 580,000 0 In 2021, JRE2 would report gross profit loss) of: 5(291,000). $(241,000) $(432,000) $0