Ventura Baseball Stadium The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on June 10,

Ventura Baseball Stadium

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on June 10, 2019 and be completed in time for the start of the 2022 season. A penalty clause of $500,000 per day of delay beyond April 3rd is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $5 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes. (Complete the table)

1. Can the project be completed by the April 3rd deadline? How long will it take?

2.What is the critical path for the project?

3.Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

Request:

  1. Answer all three questions above.
  2. Make a MS project file. The Microsoft project file should show the following - Gantt chart. - Project network diagram. - Critical path highlighted in the Gantt chart and network diagram.
ID Activity Duration Predecessor(S)
1 Baseball Stadium
2 Clear stadium site 60 days -
3 Demolish building 30 days 2
4 Set up construction site 30 days 2
5 Drive Support piling 120 days 2
6 Pour lower concrete bowl 120 days 5
7 Pour main concourse 120 days 4, 6
8 Install playing field 90 days 4, 6
9 Construct upper steel bowl 120 days 4, 6
10 Install Seats 140 days 7, 9
11 Build Luxury Boxes 90 days 7, 9
12 Install jumbotron 30 days 7, 9
13 Stadium Infrastructure 120 days 7, 9
14 Construct Steel Company 75 days 10
15 Light installation 30 days 14
16 Build roof supports 90 days 6
17 Construct roof 180 days 16
18 Install roof Tracks 90 days 16
19 Install roof 90 days 17, 18
20 Inspection 20 days 8, 11, 13, 15, 19

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ethics for the Information Age

Authors: Michael J. Quinn

7th edition

134296540, 9780134296623 , 978-0134296548

More Books

Students also viewed these General Management questions