Verification that ________ must be included in the written notification the controlling contractor provides before steel erection starts. A. The concrete is ready B. The
Verification that ________ must be included in the written notification the controlling contractor provides before steel erection starts. A. The concrete is ready B. The fall protection equipment is in working order C. All workers on site are properly trained D. The cranes are in working order