Vest Construction Companys cost of renting a crane for the last four months is as follows: Month Hours of Operation Rental Cost January 35 $1,200
Vest Construction Companys cost of renting a crane for the last four months is as follows:
Month | Hours of Operation | Rental Cost |
January | 35 | $1,200 |
February | 42 | $1,350 |
March | 45 | $1,400 |
April | 40 | $1,290 |
Using the high-low method, what is the companys estimated variable and fixed component of operating expenses?