View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time
View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time Pessimistic Time Immediate Activity Estimate(weeks) Estimates (weeks) Estimates (weeks) Predecessor(s) A 2 3 5 none B 2.5 4 5 A C 5 7 8 A D 3 5 7 B,C E 3 6 14 B,C F 2 5 8 D G 4 5 6 E H 6 6 8 F | 5 8 10 G