Question
Virginia is the productivity planner of Xerox Photocopier and she wants to determine the minimum number of balanced workstations required to maximize operations efficiency. There
Virginia is the productivity planner of Xerox Photocopier and she wants to determine the minimum number of balanced workstations required to maximize operations efficiency. There are 8 working hours per day and the demand is 39 units per day. There are nine tasks to be done per unit of photocopier. The time needed to finish task A is 10 minutes, B is 9 minutes, C is 5 minutes, D is 4 minutes, E is 10 minutes, F is 3 minutes, G is 5 minutes, H is 11 minutes, and I is 7 minutes. The predecessor/s of task B is A, C is B, D is B, E is A, F are C and D, G is F, H is E, and I are G and H.
1.How many workstations should be created based on most following or preceding tasks?
2.What is the efficiency per station?
3.What is the overall efficiency?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started