VMS has 3 screen printing machines and each one is capable of producing 680 sheets per hour. The machines each operate 40 hours per week.
VMS has 3 screen printing machines and each one is capable of producing 680 sheets per hour. The machines each operate 40 hours per week. Last week, machine \#1 produced 22,000 sheets, machine \#2 produced 23,200 sheets, and machine \#3 produced 24,800 sheets. VMS's total capacity utilization rate was %. Answer as a PERCENTAGE without the % sign. So if you calculate 0.6543 , answer like 65.43 (no \% sign)