WACC = 8% Period Project 1 Project 2 0 -$200 -$75 1 $100 $100 2 $75 $25 3 $80 4 5 6 Based on the
WACC = 8% Period Project 1 Project 2 0 -$200 -$75 1 $100 $100 2 $75 $25 3 $80 4 5 6
Based on the information in the table, what is the replacementchain NPV for Project 1?
$20.40
$40.80
$43.91
$36.59
WACC = | 8% | |
Period | Project 1 | Project 2 |
0 | -$200 | -$75 |
1 | $100 | $100 |
2 | $75 | $25 |
3 | $80 | |
4 | ||
5 | ||
6 |
Based on the information in the table, what is the replacementchain NPV for Project 1?
$20.40 |
$40.80 |
$43.91 |
$36.59 |