Question

1 Approved Answer

Waltner Corporation's management reports that its average delivery cycle time is 33 days, its average throughput time is 13.9 days, its manufacturing cycle efficiency (MCE)

Waltner Corporation's management reports that its average delivery cycle time is 33 days, its average throughput time is 13.9 days, its manufacturing cycle efficiency (MCE) is 0.32, its average move time is 0.4 day, and its average queue time is 7.00 days.

Required:
a. What is the wait time? (Round your answer to 1 decimal place.)

Wait time days

b. What is the process time? (Round your answer to 1 decimal place.)

Process time days

c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)

Inspection time days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of External Auditing

Authors: Brenda Porter, David Hatherly, Jon Simon

3rd Edition

0470018259, 9780470018255

More Books

Students also viewed these Accounting questions