Question
Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Budget
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report.
Budget | Actual | Variance | Favourable (F)/ Unfavourable (U) | |||||
Production in units | 334,000 | 349,000 | 15,000 | F | ||||
Production costs: | ||||||||
Direct material | $699,029 | $707,184 | $(8,155) | U | ||||
Direct labour | 1,586,500 | 1,623,380 | (36,880) | U | ||||
Variable overhead costs | 133,600 | 138,869 | (5,269) | U | ||||
Fixed overhead costs | 200,400 | 195,845 | 4,555 | F | ||||
Total production costs | $2,619,529 | $2,665,278 | $(45,749) | U |
The manager immediately called the production supervisor, demanding an explanation for the large unfavourable variance for the quarter. The production supervisor was puzzled. He thought the cost-cutting measures they had incorporated were beginning to work. He certainly wasnt expecting such a large discrepancy. The standard rates the plant was using with its normal costing system are summarized below.
Volume | Cost | |||||
Direct material | 1.30 | kg per unit | $1.60 | per kg | ||
Direct labour | 0.25 | hour per unit | $19.00 | per hour | ||
Predetermined overhead rate: | ||||||
Variable | 0.25 | hour per unit | $1.60 | per hour | ||
Fixed | 0.25 | hour per unit | $2.40 | per hour |
Other relevant information:
1. | A total of 461,000 kg of direct materials were purchased during the quarter at a cost of $1.80 per kilogram. | |
2. | A total of 441,990 kg of direct materials were used in production to manufacture 349,000 units. | |
3. | Payroll recorded 86,350 direct labour hours at an average cost of $18.80 per hour. |
Calculate the following production variances.
Material price variance | $ | Neither favourable nor unfavourableFavourableUnfavourable | |
Material quantity variance | $ | UnfavourableFavourableNeither favourable nor unfavourable | |
Labour price variance | $ | Neither favourable nor unfavourableFavourableUnfavourable | |
Labour efficiency variance | $ | Neither favourable nor unfavourableFavourableUnfavourable | |
Variable overhead variance | $ | FavourableUnfavourableNeither favourable nor unfavourable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started