We cannot start sequencing project activities if we haven't _ _ _ _ _ _ _ _ _ _ _ _ _ _ yet. A
We cannot start sequencing project activities if we haven't yet.
A
determined activity durations
B
created the Gantt chart
C
created the network diagram
D
created a WBS