Question
1 Approved Answer
Week Units Total Etching Cost 1 1 0 $ 2 7 2 4 2 0 3 1 2 2 7 4 5 2 2 5
Week Units Total Etching Cost
$
$
For planning purposes, management would like to know the variable etching cost per unit and the total fixed etching cost per week.
Exercise A Part Algo
Required:
a Using the leastsquares regression method, estimate the variable etching cost per unit and the total fixed etching cost per week.
b Express these estimates in the form Y a bX