What are the critical activities, given the following information on task dependencies and timings? Task Precedence Time A - 5 B - 4 C B
What are the critical activities, given the following information on task dependencies and timings? Task Precedence Time A - 5 B - 4 C B 6 D A, B 2 E C, D 3