Question

1 Approved Answer

What are the Defense Contract Management Agency's (DCMA) three types of Earned Value Management System (EVMS) compliance reviews? a.For Cause, Performance and Validation b. Implementation,

  1. What are the Defense Contract Management Agency's (DCMA) three types of Earned Value Management System (EVMS) compliance reviews?

a.For Cause, Performance and Validation

b. Implementation, Validation and Financial

c. Validation, implementation and For Cause

d. Financial, implementation and For Cause

  1. What is the impact of FAR part 34 , Major System Acquisition, on Contract Administration Services (CAS) provided by DCMA?

  1. Directs contracting Officers to insert a clause that requires the use of Earned Value Management System on certain contracts
  2. Direct Administrative Contracting Officers (ACO) to oversee contracts that include the Earned Value Management System (EVMS) clause
  3. Makes compliance with EIA-748 guidelines enforcement optional at the discretion of DCMA
  4. Requires Contracting Officers to use Earned Value Management System (EVMS) all Letters of Delegation (LODs)

3. What is the impact of DoD instruction 5000.02, Operation of the defense Acquisition System, on government acquisition as a whole?

  1. Adopted to institute an " insight not oversight"project management philosophy
  2. Discourages Predictive Analysis practices for DCMA Functional Specialist
  3. Described as one of industry's most powerful program management documents
  4. Stipulates the EVM compliance happens at the end of contract performance

4. A common way to request a change or update to a particular Earned Value Management clause being put on contract:

  1. Contract Deficiency Report (CDR)
  2. Contract Correction Report (CCR)
  3. Contract Inadequacy Report (CIR)
  4. Contract Modification Report (CMR)

5. Lightweight Assault Reconnaissance (LAR) contract was valued at $102.7M with a Program Management Baseline (PMB) of $63.4M. How often was an integrated Program Management Report (IPMR) required for this Cost Plus Incentive Fee (CPIF) contract?

  1. BI-Monthly
  2. Quarterly
  3. Bi-Annually
  4. Monthly

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Technology Ventures From Idea To Enterprise From Idea To Enterprise

Authors: Richard C Dorf, Byers

3rd Global Edition

9780071289214

More Books

Students also viewed these Economics questions

Question

What is the difference between decision making and problem solving?

Answered: 1 week ago

Question

What conflicts of interest had to be resolved?

Answered: 1 week ago