Question
1 Approved Answer
What are the estimated slack times (in weeks) for activities A and H? ACTIVITY IMMEDIATE PREDECESSOR(S) DURATIONS (WEEKS) OPTIMISTIC MOST LIKELY PESSIMISTIC Start - AStart91521BStart132123CA6918DA233547EB192627FC232941GD142026HE,
What are the estimated slack times (in weeks) for activities A and H?
ACTIVITYIMMEDIATE PREDECESSOR(S)DURATIONS (WEEKS)OPTIMISTICMOST LIKELYPESSIMISTICStart- AStart91521BStart132123CA6918DA233547EB192627FC232941GD142026HE, F, G258EndHStep by Step Solution