Question

1 Approved Answer

What cost estimating technique would be indicated for the following situation? The program just entered he Technology Maturation and Risk Reduction phase. This method of

What cost estimating technique would be indicated for the following situation? The program just entered he Technology Maturation and Risk Reduction phase. This method of cost estimating is quick but subjective and not as precise as other cost estimating methods. Technical and cost data from similar systems exist.

A. Parametric

B. Analogy

C. Engineering

D. Actual Costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Science The Art Of Modeling With Spreadsheets

Authors: Stephen G. Powell, Kenneth R. Baker

3rd Edition

0470530677, 978-0470530672

More Books

Students also viewed these Finance questions

Question

Analyse criteria for evaluating the effectiveness of managers.

Answered: 1 week ago