Question

1 Approved Answer

What is FALSE about rough order of magnitude (ROM) budget estimates? Select an answer: a-ROMs are usually based on knowledge of similar projects. b-ROMs should

What is FALSE about rough order of magnitude (ROM) budget estimates?

Select an answer:

a-ROMs are usually based on knowledge of similar projects.

b-ROMs should have a variance of minus 10% to plus 15% of the actual cost.

c-ROMs provide an initial cost estimate to determine whether a project is viable.

d-ROMs are built at the project initiation stage.

-To build a project budget, Liam considers federal tax regulations and his company's budgeting cycle. According to the Project Management Institute, how are those two factors classified?

Select an answer:

a-as enterprise environmental factors

b-as variable cost factors

c-as non-compete factors

d-as GAAP factors

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions