WHAT IS THE AMOUNT OF THE CONTRACT ASSET (CONTRACT LIABILITY) FOR 2011 Chan Builders Inc entered into a contract with George Company to construct a

WHAT IS THE AMOUNT OF THE CONTRACT ASSET (CONTRACT LIABILITY) FOR 2011

image text in transcribed
Chan Builders Inc entered into a contract with George Company to construct a production plant. At that time, Chan Builders estimated that it would take five years to complete the facility at a total cost of P28,800,000. Chan Builders therefore, pegged the total contract price for the construction of the facility at P34,800,000. During 2010, Chan Builders incurred P7,500,000 in construction costs related to the project. Because of rising material and labor costs, the estimated cost to complete the contract at the end of 2010 amounted to P22,500,000. George was billed and paid 30% on the contract price in accordance with the contract agreement. Compute the Contract Asset (Contract Liability) for 2011

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Practicing Financial Planning

Authors: Sid Mittra, Anandi P Sahu, Brian Fischer

12th Edition

9386042851, 9789386042859

More Books

Students also viewed these Accounting questions

Question

1. Too understand personal motivation.

Answered: 1 week ago