Question
1 Approved Answer
What is the cost of a single, completed unit transferred out of sanding? Sanding department Units WIP, March 1 (100% material: 50% conversion) Units started
What is the cost of a single, completed unit transferred out of sanding?
Sanding department Units WIP, March 1 (100% material: 50% conversion) Units started in March Units completed and transferred to painting WIP, March 31 (100% material, 60% conversion) Costs WIP, March 1 Materials (100% complete) conversion (50% complete) WIP value, March:1 Costs incurred in March 70 200 150 120 $12,000 $60,000 $72,000 $30,000 $145,000 $175,000 $247,000 Materials Conversion Costs incurred in March Total costs Sanding department Units WIP, March 1 (100% material: 50% conversion) Units started in March Units completed and transferred to painting WIP, March 31 (100% material, 60% conversion) Costs WIP, March 1 Materials (100% complete) conversion (50% complete) WIP value, March:1 Costs incurred in March 70 200 150 120 $12,000 $60,000 $72,000 $30,000 $145,000 $175,000 $247,000 Materials Conversion Costs incurred in March Total costsStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started