Question

1 Approved Answer

What is the duration of the project under normal conditions? What is the total normal project cost for completing the project under normal conditions? What

What is the duration of the project under normal conditions?

What is the total normal project cost for completing the project under normal conditions?

What activities are on the critical path?

What is the cost unit for Activity E?

What is the crash unit cost for Activity D?

The owner wants to shorten the total duration by 2 weeks. Which activity should be shortened?

What will be the crash cost for this shortening by two weeks this activity?

What is the total crash cost if we were to crash the whole schedule without doing any easing of activities?

The following table includes activities, their durations for both normal and crash time as well as the associated costs.

Activity Predecessor Normal Duration Normal Cost Crash time Crash cost
A - 6 100 6 100
B - 8 200 8 200
C A 4 200 2 800
D B,C 9 2000 5 4500
E B 9 500 4 2000
F E 10 1500 6 3500
G C 8 800 5 2000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Fundamentals Of Fashion Management

Authors: Susan Dillon

2nd Edition

1474271219, 978-1474271219

More Books

Students also viewed these General Management questions

Question

3. Define the roles individuals play in a group

Answered: 1 week ago