What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? Time Predecessor Activity 15 A
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? Time Predecessor Activity 15 A B. 17 A 8 D 7 A E 4 B F 8 C D G EF H 17 G Ltfen birini sein: A. 15 B. 17 C21 D. 19