Question

1 Approved Answer

What is the estimated project budget ( total normal cost ) ? What is the additional cost for reducing the project time to the required

What is the estimated project budget (total normal cost)? What is the additional cost
for reducing the project time to the required 35 weeks? Which specific tasks do you recommend
crashing in order to achieve this milestone? After crashing the project, what is/are the critical path(s)?
(Hint: Use the expected time of each activity as the normal time for each activity, and note that the
number of weeks can be non-integer numbers). Please summarize your analysis in Table 3. Use this heders for the chart with the solutions: Activity to be crashed, # weeks to be crashed, Total cost of activity to be crashed, Total additional cost of project crashing, Critical path(s).Exhibit 1
PROJECT DESCRIPTION AND TIME ESTIMATES (WEEKS)
Source: Created by authors.
Exhibit 2
PROJECT CRASH DATA
Source: Created by authors.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions