Question
What is the expected time ( te ) for each activity ? Round your calculations to the nearest second decimal point. Show all your work.
What is the expected time (te) for each activity? Round your calculations to the nearest second decimal point. Show all your work.
What is the critical path, and how long is this project expected to last? Show all your work.
What is the variance of the critical path? Round your calculations to the nearest second decimal point. Show all your work.
Suppose you have a personal goal of completing this project in 31 weeks. What is the probability that you will be able to meet this goal? Round your analysis to the nearest second decimal point. Show all your work.
The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. Activity Optimistic (a) Most Likely (m) Pessimistic (b) A B C D E F G H 3 7 5 3 2 5 2 4 5 9 9 6 6 7 4 7 9 11 17 8 12 10 5 8 Use the above information to do your analysis in the next question.
Step by Step Solution
3.38 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
To calculate the expected time for each activity we can use the PERT Program Evaluation and Review Technique formula te a 4m b 6 where te expected tim...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started