Question

1 Approved Answer

what is the free float for activity E and respect to activity H show calcutions As a project manager for Nando's you must manage a

what is the free float for activity E and respect to activity H show calcutions

image text in transcribed

As a project manager for Nando's you must manage a project with activities and their respective durations as listed in the table below: 2.1 Construct a network diagram to analyses your project. (11) (NB: The network diagram needs to have all the values otherwise zero marks will be awarded) 2.2 What is the total project duration time? (1) 2.3 Identify the critical path on your network diagram. (1) 2.4 When is the latest time that activity G must be completed in order not to experience any delays in the project? What is the earliest time that activity D can possibly be completed? (1) W.6 What is the free float for activity E with respect to activity H ? Show your calculations. (4) What would the implication to the project duration time be if there was a delay of 2 months in completing activity F? (1)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

1. What is the core product that Revlou sells?

Answered: 1 week ago