What is the minimum amount of time needed to complete the renovation project? Also, what are the critical activities and the critical path ( s

What is the minimum amount of time needed to complete the renovation project? Also, what
are the critical activities and the critical path(s) of the project?
d. Suppose now that we are given the following crashing information. For each week that we are
able to reduce the project completion time, we are paid an extra $800. Using the greedy method
learned in class, crash the project for as many weeks as it is profitable to do so. Clearly show which
activities you will crash for each week, the cost of crashing for each week, and all of the critical
paths at the end of each week. If it becomes no longer profitable to crash the project, then clearly
explain why.
Activity Immediate Normal Duration Crash Duration Normal Crash Crash Cost
Predecessors (weeks)(weeks) Cost Cost per Week
A 21 $100 $1,100 $1,000
B A 32 $300 $1,300 $1,000
C B 43 $300 $1,000 $700
D A 63 $400 $3,100 $900
E C,D 107 $700 $1,600 $300
F C,D 1110 $800 $1,400 $600
G C,D 54 $400 $1,100 $700
H G 76 $600 $1,200 $600

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management in the Supply Chain Decisions and Cases

Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein

6th edition

73525243, 978-0073525242

More Books

Students also viewed these General Management questions