Question

1 Approved Answer

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Activity Normal Time (

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Activity
Normal Time(days)
Crash Time(days)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
B
C
D
A
E
C
Part 2
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)
Activity
Each Activity Should be Reduced BY
(days)
A
1
B
0
C
1
D
2
E
3
Part 3
The total cost of crashing the project by 4 days is $
enter your response here. (Enter your response as a whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions