Question

1 Approved Answer

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Activity Normal Time (

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Activity
Normal Time(days)
Crash Time(days)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
5
4
$800
$1,100
B
8
6
$250
$400
C
4
3
$600
$650
D
6
4
$750
$1,500
A
E
8
5
$1,200
$1,650
C
Part 2
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions