What is the net present value (NPV) of a project whose cost is $ 45,000 and that is expected to generate a cash flow after
What is the net present value (NPV) of a project whose cost is $ 45,000 and that is expected to generate a cash flow after taxes of $ 14,000 in the first 2 years, $ 10,000 in the next 2 years, and $ 8,000 in the 5th year with a required rate of return of 8%?