Question
1 Approved Answer
what is the payback period for a project that costs $1,000 at time 0, and has cash flows of $500 at time 1, $400 at
what is the payback period for a project that costs $1,000 at time 0, and has cash flows of $500 at time 1, $400 at time 2, $300 at time 3, and $100 at time 4.
A. 2.33 years
B. 2.95 years
C. 3.33 years
D. This project never pays back
E. More information is needed in order to calculate the payback period