Question

1 Approved Answer

What is the probability of completing this project within 25 weeks? Assume that the expected completion time is 26 weeks. Optimistic, Most probable, and pessimistic

What is the probability of completing this project within 25 weeks? Assume that the expected completion time is 26 weeks.

Optimistic, Most probable, and pessimistic Activity time Estimates (in Weeks)
ActivityOptimistic (a)Most Probable (m)Pessimistic (b)
A4.007.0012.00
B1.002.005.00
C2.004.007.00
D3.005.0011.00
E2.004.006.00
F1.503.005.00
G1.504.004.50
H2.504.007.50
I1.503.003.50
J1.002.003.00


ActivityEarliest Start (ES)Latest Start (LS)Earliest Finish  (EF)Latest Finish (LF)
A0066
B0729
C610913
D671112
E6699
F9131115
G11121415
H991313
I13131515
J15151717

Step by Step Solution

3.37 Rating (153 Votes )

There are 3 Steps involved in it

Step: 1

To calculate the probability of completing the project within 25 weeks you can use the Critical Path ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

More Books

Students also viewed these General Management questions

Question

What are the major steps in the simulation process?

Answered: 1 week ago