The following represents a project that should be scheduled using CPM: a. Draw the network. b. What

Question:

The following represents a project that should be scheduled using CPM:
Times (days) Immediate Predecessors am Activity A 2 3 B 1 2 3 3 4 11 4 c,d G d,e 4 6. f,g Н 2 4 4. 3. 2. 3. 3.

a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?