What is the probability that the project will take more than 20 weeks? TRUE or FALSE which is the right? If we use TRUE, I
What is the probability that the project will take more than 20 weeks?
TRUE or FALSE which is the right?
If we use TRUE, I think it means "not more than 20 weeks"?
Mean:19
Variance:5.666667
= NORMDIST(20, 19, SQRT(5.666667), TRUE)
= NORMDIST(20, 19, SQRT(5.666667), FALSE)