Question

1 Approved Answer

What is the slack of activity c? 0 4 2 1 begin{tabular}{|c|c|c|} hline Activity & Immediate Predecessors & Activity Time (days) hline A &

image text in transcribed

What is the slack of activity c?

0

4

2

1

\begin{tabular}{|c|c|c|} \hline Activity & Immediate Predecessors & Activity Time (days) \\ \hline A & - & 4 \\ \hline B & - & 7 \\ \hline C & B & 6 \\ \hline D & A, B & 10 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Emergency Management

Authors: Jane A Bullock, George D Haddow

7th Edition

0128171391, 9780128171394

More Books

Students also viewed these General Management questions

Question

Do not pay him, wait until I come

Answered: 1 week ago

Question

Do not get married, wait until I come, etc.

Answered: 1 week ago

Question

Do not come to the conclusion too quickly

Answered: 1 week ago