What is the Total Cost of Labor to install 13,000 ft of pipes given: Crew consists of 2 Pipefitters and 4 Laborers, at hourly rates
What is the Total Cost of Labor to install 13,000 ft of pipes given: Crew consists of 2 Pipefitters and 4 Laborers, at hourly rates of $49 and $27 respectively Productivity rate of 5.0 labor-hours per 100 ft of pipe Productivity factor of