When a breach has occurred and the plaintiff successfully seeks a court order to force the defendant to perform under the contract, that order is
When a breach has occurred and the plaintiff successfully seeks a court order to force the defendant to perform under the contract, that order is called an order for:
A) | Specific performance. | |
B) | Injunctive relief. | |
C) | A writ. | |
D) | None of the above. |