Question
1 Approved Answer
When communicating uncertainty in project risk messages, the content should be: The potential cost of the risk to the project Expressed in project management risk
When communicating uncertainty in project risk messages, the content should be: The potential cost of the risk to the project Expressed in project management risk codes Explicit and not left to implied recognition by the receiver Limited to messages between the project manager and the delivery team