Question

1 Approved Answer

When developing a project schedule, total float ( or slack ) refers to the amount of time a schedule activity may be delayed from its

When developing a project schedule, total float (or slack) refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project finish date.
A) True
B) False

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Aviation Marketing And Management

Authors: C. Daniel Prather

3rd Edition

9781575243016

More Books

Students also viewed these General Management questions

Question

How appropriate is it to conduct additional research?

Answered: 1 week ago

Question

What information remains to be obtained?

Answered: 1 week ago