When is a contingency plan most useful in a project? Select one: a. When the risk is so intolerable to the stakeholders it cannot be
When is a contingency plan most useful in a project?
Select one:
a. When the risk is so intolerable to the stakeholders it cannot be allowed to happen unchecked
b. When the risk that occurs will result in scope creep
c. When there are numerous low priority risks
d. When there are enough technical resources to create it