Question: When is a ( Scrum ) Sprint over? Mark only one oval. When all Product Backlog items meet their definition of done. When the Product
When is a Scrum Sprint over?
Mark only one oval.
When all Product Backlog items meet their definition of done.
When the Product Owner says it is done.
When all the tasks are completed.
When the Sprint timebox expires.