Question: When job 711 was completed, direct materials totaled $6,632 for direct labor, $8,558, and factory overhead, $6,205, respectively. Units produced totaled 1,945. What are unit

When job 711 was completed, direct materials totaled $6,632 for direct labor, $8,558, and factory overhead, $6,205, respectively. Units produced totaled 1,945. What are unit costs?