When preparing for a Defense Acquisition Board (DAB) review, the OSD Cost Assessment Program Evaluation (CAPE) establishes a timeline to ensure that they have sufficient
When preparing for a Defense Acquisition Board (DAB) review, the OSD Cost Assessment Program Evaluation (CAPE) establishes a timeline to ensure that they have sufficient time and information to create their Independent Cost Estimate (ICE). How many days are required prior to OIPT to conduct the Planning/Kick-off meeting?
A) 28 days
B) 45 days
C) 180 days
D) none of these are correct