When procuring materials for a project Owners typically do not pay for materials ordered until it arrives on the construction site. Sometimes to lock in
When procuring materials for a project Owners typically do not pay for materials ordered until it arrives on the construction site. Sometimes to lock in prices and save money Contractors will order materials that they may not have room to store on the site and store them offsite. In order to get paid for this off site material what must the contractor typically provide