When the project manager does not have detailed information on which to base time estimates and/or there is sufficient relevant historical data available, he/she should
When the project manager does not have detailed information on which to base time estimates and/or there is sufficient relevant historical data available, he/she should consider using which type of estimating method? O parametric O conventional O bottom-up O analogous